Min stripping time (hours)
14.7
Min stripping time (days)0.6
Required strength (psi)500
Est. strength at strip (psi)543
% of 28-day strength13.6
Maturity (°F·hr)752
Member LabelVertical (wall/column)
How to Use This Calculator
- Enter the Ambient Temperature in °F and the 28-Day Design Strength of the concrete mix.
- Select the Member Type (vertical, slab soffit, or beam/joist soffit) and Cement Type.
- Indicate whether Wet Curing or blankets are being used — this reduces minimum strip time.
- Review Minimum Stripping Time in hours and days before removing any formwork.
- Check Estimated Strength at Strip and % of 28-Day Strength to confirm structural adequacy.
Ad Placeholder
Related Calculators
Wall Form Pressure Calculator
Lateral concrete pressure from pour rate and temperature per ACI 347R.
Reshoring Calculator
Calculate reshore spacing and loads for multi-story concrete construction.
Column Form Calculator
Calculate column form plywood area, clamp spacing, and concrete volume.
Shore Tower Design Calculator
Calculate shore post spacing and load from slab thickness and shore capacity.
Ad Placeholder