Erection Sequence Calculator

Plan precast erection: estimate crane picks per day, total erection days, crew size, and project cost.

Inputs

lbs
lbs
min
hrs
%
$/hr
$/hr

Results

Picks per day

9

Total erection days6 days
Min crane capacity22,500 lbs
Crew size6 persons
Crane cost$16,800
Labor cost$24,480
Erection cost$41,280
Cost per panel$826
Mob/demob estimate$10,000
Total project cost$51,280
Crane utilization92.6%
Cost Per Pick$825.6
How to Use This Calculator
  1. Enter the total number of precast panels and the average and heaviest panel weights in lbs.
  2. Set the cycle time per crane pick in minutes (including set, plumb, and weld) and work hours per day.
  3. Enter the weather/delay factor (%) and the crane hourly rate and ironworker burdened labor rate.
  4. Read Picks per Day and Total Erection Days to set your schedule.
  5. Check Min Crane Capacity (lbs) — this is the heaviest piece times 1.25 and sets the minimum crane size.
  6. Review Erection Cost, Labor Cost, and Total Project Cost for budget planning and subcontractor negotiation.