Skip to main content
Calcimator

Erection Sequence Calculator

Plan precast erection: estimate crane picks per day, total erection days, crew size, and project cost.

About this calculator

Precast erection schedules run on a simple rhythm: pick, swing, set, plumb, connect, swing back, repeat, and this calculator turns that cycle time into a daily pick count, then divides total panels by that count to get erection days. Weather and delay time comes off the top as a percentage of the work day before the cycle-time math runs, so a 10% weather factor on an 8-hour day leaves 7.2 productive hours to divide into picks — not 8 hours minus 10% of the final pick count. Required crane capacity is driven entirely by the single heaviest panel in the job, not the average, with a 1.25 multiplier for rigging and dynamic pick loads; the average panel weight input mostly just sets a floor under the heaviest-panel figure; if you enter a heaviest panel lighter than the average, the calculator quietly raises it to match the average, since a project's heaviest single panel can never really be less than the mean panel weight.

Crew size is fixed at six regardless of job size — a typical crane operator, oiler, two connectors, a signalman, and a plumber — so it does not flex for larger or smaller crews the way the cost and schedule numbers do. Mobilization and demobilization cost is a step function of the required crane capacity, jumping between four price bands rather than scaling smoothly, which is worth knowing if your required capacity sits close to one of those band edges.

Inputs

lbs
lbs
min
hrs
%
$/hr
$/hr

Results

Picks per day

9

Total erection days6 days
Min crane capacity22,500 lbs
Crew size6 persons
Crane cost$16,800.00
Labor cost$24,480.00
Erection cost$41,280.00
Cost per panel$826.00
Mob/demob estimate$10,000.00
Total project cost$51,280.00
Crane utilization92.6%
Cost Per Pick$825.60
How to Use This Calculator
  1. Enter the total number of precast panels and the average and heaviest panel weights in lbs.
  2. Set the cycle time per crane pick in minutes (including set, plumb, and weld) and work hours per day.
  3. Enter the weather/delay factor (%) and the crane hourly rate and ironworker burdened labor rate.
  4. Read Picks per Day and Total Erection Days to set your schedule.
  5. Check Min Crane Capacity (lbs) — this is the heaviest piece times 1.25 and sets the minimum crane size.
  6. Review Erection Cost, Labor Cost, and Total Project Cost for budget planning and subcontractor negotiation.

How the result changes with Cycle time per pick

Cycle time per pickPicks per day
2318
3412
686
1133

What each input means

Total panels/pieces
Total number of precast pieces to erect.
Average panel weight
Average weight per precast piece.
Heaviest panel weight
Weight of the heaviest piece (determines crane size).
Cycle time per pick
Average time per crane pick including set, plumb, and weld.
Work hours per day
Productive work hours per day.
Weather/delay factor
Estimated percentage of time lost to weather/delays.
Crane hourly rate
All-in crane rental rate per hour.
Labor rate per person
Burdened labor rate per crew member per hour.

What each result means

Picks per day
Number of precast pieces that can be set per day.
Total erection days
Calendar work days to complete erection.
Min crane capacity
Minimum crane capacity (heaviest piece × 1.25).
Crew size
Recommended erection crew size.
Crane cost
Total crane rental cost.
Labor cost
Total erection labor cost.
Erection cost
Combined crane and labor cost.
Cost per panel
Average erection cost per panel.
Mob/demob estimate
Estimated crane mobilization and demobilization cost.
Total project cost
All-in erection cost including mob/demob.
Crane utilization
Crane utilization efficiency.

How this is calculated

Worked example, using the default values

  1. Identify Input Parameters
    4 parameters
    Total panels/pieces = 50, Average panel weight = 12000, Heaviest panel weight = 18000, Cycle time per pick = 45 = 8 input(s) provided
  2. Calculate Picks per day
    Picks per day = max(1, picksPerDay)
    9 = 9
  3. Calculate Total erection days
    Total erection days
    6 = 6
  4. Calculate Min crane capacity
    Min crane capacity = heaviestPanel * 1.25
    22500 = 22500

Engine last updated . Checked against 2 independently-derived tests — how we verify calculators. Built by Paul Gunder, a software engineer, not a licensed financial, medical, or legal professional.

Frequently Asked Questions

Why doesn't average panel weight change the crane capacity or cost?

Because required crane capacity is set by the single heaviest panel on the job, not the average — a crane sized for the mean weight could still fail to lift the heaviest piece. Average panel weight only matters as a floor: if you type in a heaviest-panel figure that's lower than the average, the calculator raises it back up to match, since the true heaviest panel can never be lighter than the mean.

How is weather delay time actually applied to the schedule?

It's subtracted from the work day before the pick-rate math runs, not from the final pick count. An 8-hour day with a 10% weather factor becomes 7.2 productive hours, which then gets divided by cycle time to find picks per day — so weather delay compounds through the whole schedule rather than just shaving picks off the end of an otherwise full day.

Does crew size scale up on bigger erection jobs?

No — this calculator uses a fixed six-person crew (crane operator, oiler, two connectors, signalman, and plumber) regardless of total panel count or job size. Larger projects that run parallel crews or add a second crane need to be modeled as separate erection sequences, since the cost and schedule math here assumes one crew working one crane.

Why does mobilization cost jump instead of scaling smoothly with crane size?

Mob/demob pricing here uses four flat price bands tied to required crane capacity (roughly $5,000 up to $10,000 up to $18,000 up to $25,000) rather than a continuous rate, which mirrors how crane rental quotes actually work — a bigger class of crane means a different rig and crew to bring it in, not a proportionally bigger version of the same machine.

The questions that sit next to this one — chosen by subject, including calculators filed under a different category.

More in Construction & Building Trades.