Estimate excavation costs based on volume, soil type, machine rates, and hauling for earth, rock, or mixed material.

About this calculator

Cost per Cubic Yard is the most stable number this calculator produces: because Machine Cost and Hauling Cost are both exactly proportional to Excavation Volume — Machine Hours divides volume by a production rate, and Hauling Cost is volume times a flat per-yard haul rate — Total Cost scales in lockstep with volume too, which means Cost per Cubic Yard stays essentially constant no matter how large or small the job is. What actually moves Cost per Cubic Yard is Soil/Material Type and the two rate inputs: Rock applies a 2.5x production penalty (digging is slower) plus a higher $15/yd haul rate versus $10/yd for earth or mixed soil, so switching from Earth to Rock raises the per-yard cost substantially — about 1.77x at this calculator's default Machine Rate and Base Production Rate — even though Volume never changed. That ratio isn't fixed, though: it climbs above 2x only once Machine Rate divided by Base Production Rate exceeds roughly 10 (a comparatively expensive machine paired with a slow production rate). Base Production Rate has an inverse relationship with cost — a faster rig (higher cu yd/hr) needs fewer Machine Hours, which lowers Machine Cost directly.

Machine Rate scales Machine Cost up in direct proportion, same as any hourly rental rate would. Machine Type is provided as a label for your own reference on the estimate but does not change any calculated value here — Base Production Rate is what actually drives productivity in this model, so pick the number appropriate to whichever machine you select. This is a materials/equipment estimate only; it does not include mobilization, permits, or utility locate costs.

Inputs

cu yd
$/hr
cu yd/hr

Results

Machine Cost

$1,875.00

≈ 14 pairs of sneakers

Total Cost

$6,875.00

≈ 7 smartphones

Cost per Cubic Yard

$13.75

Machine Hours12.5 hrs
Hauling Cost$5,000.00
How to Use This Calculator
  1. Enter Excavation Volume in cubic yards — calculate this with the Trench Volume calculator first.
  2. Select Soil/Material Type: soft soil is fastest; rock is slower to dig and costs more to haul.
  3. Note the Machine Type for your own records, then set Base Production Rate and Machine Rate to match the equipment you'll actually use.
  4. Review Machine Cost and Hauling Cost to see the split between equipment time and material removal.
  5. Compare Cost per Cubic Yard across scenarios to shop soil type and machine assumptions against contractor bids.

How the result changes with Base Production Rate

Base Production RateMachine CostTotal CostCost per Cubic Yard
20$3,750.00$8,750.00$17.50
30$2,500.50$7,500.50$15.00
60$1,249.50$6,249.50$12.50
100$750.00$5,750.00$11.50

What each input means

Excavation Volume
Total volume to be excavated in cubic yards.
Soil/Material Type
Material type affects production rate and hauling cost.
Machine Type
Equipment type used for excavation.
Machine Rate
Hourly rental or operating cost of the machine with operator.
Base Production Rate
Production rate in normal soil conditions (adjusted for soil type).

How this is calculated

Worked example, using the default values

  1. Identify Input Parameters
    4 parameters
    Excavation Volume = 500, Soil/Material Type = 1, Machine Type = 2, Machine Rate = 150 = 5 input(s) provided
  2. Calculate Machine Cost
    Machine Cost
    1875 = $1,875
  3. Calculate Total Cost
    Total Cost
    6875 = $6,875
  4. Calculate Cost per Cubic Yard
    Cost per Cubic Yard
    13.75 = $13.75
  5. Calculate Machine Hours
    Machine Hours
    12.5 = 12.5
  6. Calculate Hauling Cost
    Hauling Cost
    5000 = $5,000

Engine last updated . Checked against 2 independently-derived tests — how we verify calculators. Built by Paul Gunder, a software engineer, not a licensed financial, medical, or legal professional.

Frequently Asked Questions

Why is Cost per Cubic Yard the most stable number this calculator produces, even across very different job sizes?

Because both Machine Cost and Hauling Cost scale exactly in proportion to volume — Machine Hours is volume divided by a fixed production rate, and Hauling Cost is volume times a flat per-yard rate — so Total Cost grows at the same rate as Volume. Dividing one by the other leaves a per-yard figure that barely moves regardless of job size.

Is Machine Type more than just a label on the estimate?

No — Machine Type is a label for your own reference only. The productivity this calculator actually uses comes from Base Production Rate, so if you select a different machine, update Base Production Rate to match its real output rather than relying on the Machine Type selection to do it for you.

Why does rock cost so much more per cubic yard than earth?

Rock applies two penalties at once: a 2.5x production-rate multiplier that slows digging (fewer cubic yards per machine hour), and a higher $15/yd hauling rate versus $10/yd for earth or mixed soil. Both push Cost per Cubic Yard up together — about 1.77x at this calculator's default rate and production inputs — and the ratio only climbs past 2x once Machine Rate divided by Base Production Rate rises above roughly 10.

What's the relationship between Base Production Rate and Machine Cost?

Inversely proportional — Machine Hours is Volume divided by the effective production rate, so a higher Base Production Rate means fewer hours and a lower Machine Cost for the same job. A rig rated at 80 cu yd/hr finishes in half the time, and roughly half the machine cost, of one rated at 40 cu yd/hr.