Line Balancing Calculator

Optimize workstation task assignment by calculating line efficiency, balance delay, and minimum station count.

Inputs

sec
sec

Results

Line Efficiency

83.3%

Minimum Stations Needed5
Balance Delay16.7%
Total Idle Time per Cycle60 sec
Avg Idle per Station10 sec
Smoothness Index24.49
Output per Hour60 units
How to Use This Calculator
  1. List all workstation tasks with their cycle times in seconds.
  2. Enter the required takt time (customer demand rate) in seconds.
  3. Review the line balance efficiency percentage and idle time per station.
  4. Redistribute tasks to workstations to minimize the number of stations while meeting takt time.
  5. Target a line balance efficiency above 85% — below 75% indicates significant rebalancing opportunity.