Agile Team Capacity Calculator

Calculate sprint capacity accounting for ceremonies and focus factor.

Inputs

days
hrs
days
hrs
%

Results

Sprint Capacity (hours)

205.8 hrs

Estimated Story Points41
Total Available Hours342 hrs
Capacity Per Person34.3 hrs
Total Available Days57
Ceremony Overhead48 hrs
Utilization Rate70%
Optimal Team Size5
How to Use This Calculator
  1. Enter the number of team members available for the sprint.
  2. Set the sprint length in days and the working hours per day.
  3. Input the average focus factor percentage (typical teams: 70–80%).
  4. Enter planned time off or ceremony hours.
  5. Review the total available sprint capacity in person-hours and story-point equivalent.

How the result changes with Sprint Length

Sprint LengthSprint Capacity (hours)
3.952.1 hrs
11231 hrs
20457.8 hrs
27634.2 hrs

What each input means

Team Members
Number of team members in the sprint.
Sprint Length
Sprint duration in working days.
Productive Hours / Day
Productive hours per person per day.
Total PTO Days (team)
Total PTO/sick days across the team this sprint.
Ceremony Hours (per person)
Hours per person spent in sprint ceremonies.
Focus Factor
Percentage of available time spent on sprint work.

How this is calculated

Worked example, using the default values

  1. Identify Input Parameters
    4 parameters
    Team Members = 6, Sprint Length = 10, Productive Hours / Day = 6, Total PTO Days (team) = 3 = 6 input(s) provided
  2. Calculate Sprint Capacity
    Sprint Capacity
    205.8 = 205.8
  3. Calculate Estimated Story Points
    Estimated Story Points
    41 = 41
  4. Calculate Total Available Hours
    Total Available Hours
    342 = 342

Engine last updated . Checked against 2 independently-derived tests how we verify calculators.

The questions that sit next to this one — chosen by subject, including calculators filed under a different category.

More in Business & Entrepreneurship.