Earned Value Management Calculator
Perform Earned Value analysis to track project cost and schedule performance. Calculate CPI, SPI, EAC, ETC, and variance metrics.
Inputs
Results
Earned Value (EV)
$400,000.00
≈ 10 Teslas
Cost Performance Index
0.89
Estimate at Completion
$1,124,859.39
≈ 3 average U.S. homes
How to Use This Calculator
- Enter Budget at Completion (BAC), Percent Complete, and Actual Cost (AC).
- Set Planned Progress.
- Review Earned Value (EV) ($), Cost Performance Index, and Estimate at Completion ($).
- Use Schedule Performance Index and Cost Variance ($) to inform your decision.
- Use the chart to visualize the results and explore different scenarios by adjusting inputs.
How the result changes with Budget at Completion (BAC)
| Budget at Completion (BAC) | Earned Value (EV) | Cost Performance Index | Estimate at Completion |
|---|---|---|---|
| $10,000,900.00 | $4,000,360.00 | 8.89 | $1,124,960.63 |
| $35,000,650.00 | $14,000,260.00 | 31.11 | $1,124,988.75 |
| $65,000,350.00 | $26,000,140.00 | 57.78 | $1,125,001.73 |
| $90,000,100.00 | $36,000,040.00 | 80 | $1,125,001.25 |
What each input means
- Budget at Completion (BAC)
- Total approved project budget.
- Percent Complete
- Actual physical percent complete of the work.
- Actual Cost (AC)
- Total costs actually incurred to date.
- Planned Progress
- Percent of work that should be done per the baseline schedule.
What each result means
- Earned Value (EV)
- Value of work actually completed (BAC × % Complete).
- Cost Performance Index
- Cost efficiency ratio (>1 = under budget, <1 = over budget).
- Schedule Performance Index
- Schedule efficiency ratio (>1 = ahead, <1 = behind).
- Cost Variance
- EV minus AC. Positive means under budget.
- Schedule Variance
- EV minus PV. Positive means ahead of schedule.
- Estimate at Completion
- Projected total cost based on current CPI.
- Estimate to Complete
- Remaining cost to finish the project.
- Variance at Completion
- Projected budget surplus or overrun.
- To-Complete Performance Index
- Required CPI for remaining work to meet BAC.
How this is calculated
Worked example, using the default values
- Identify Input Parameters4 parametersBudget at Completion (BAC) = 1000000, Percent Complete = 40, Actual Cost (AC) = 450000, Planned Progress = 45 = 4 input(s) provided
- Calculate Earned ValueEarned Value400000 = $400,000
- Calculate Cost Performance IndexCost Performance Index0.889 = 0.889
- Calculate Estimate at CompletionEstimate at Completion1124859.39 = $1,124,859.39
- Calculate Schedule Performance IndexSchedule Performance Index0.889 = 0.889
- Calculate Cost VarianceCost Variance-50000 = $-50,000
Engine last updated . Checked against 2 independently-derived tests — how we verify calculators.
Related Calculators
The questions that sit next to this one — chosen by subject, including calculators filed under a different category.
Critical Path Method Calculator
Estimate project duration using Critical Path Method (CPM). Calculate critical path length, total float, and schedule compression potential.
Construction ManagementConstruction Bid Calculator
Build a construction bid price from material, labor, equipment, overhead, and profit margin. See the full cost breakdown.
Project ManagementEarned Value Calculator
Calculate CPI, SPI, EAC, and ETC for project performance tracking.
Construction ManagementChange Order Impact Calculator
Calculate the full cost impact of a construction change order including markup, schedule delay costs, and new contract value.
More in Construction & Building Trades.