Entitlement Timeline Calculator
Estimate months from raw land to building permit through the entitlement process.
Inputs
months
months
months
months
months
months
%
Summary
Effective Timeline
17.5 months
Timeline (Years)
1.46 years
Sequential Total20 months
Months Saved (Concurrent)2.5
Longest Phase6 months
Pre-App % of Total10%
Environmental % of Total30%
How to Use This Calculator
- Enter months for each phase: Pre-Application, Environmental Review, Zoning Approval, Plat Approval.
- Set Utility Approvals and Building Permit months for the final stages.
- Set Concurrent Processing % — the degree to which phases can overlap to compress the timeline.
- Review Effective Timeline in months and years to plan financing, land carry, and marketing start.
- Compare Sequential Total vs. Effective Timeline to quantify the benefit of pursuing concurrent approvals.
- Use this estimate in pro forma financial models for land carry cost calculation.
How the result changes with Environmental Review
| Environmental Review | Effective Timeline | Timeline (Years) |
|---|---|---|
| 3.6 | 15.1 months | 1.26 years |
| 13 | 24.5 months | 2.04 years |
| 23 | 34.5 months | 2.88 years |
| 32 | 43.5 months | 3.63 years |
What each input means
- Pre-Application
- Time for pre-application meetings, feasibility, and initial surveys.
- Environmental Review
- Time for environmental assessments, NEPA, wetland delineation.
- Zoning Approval
- Time for zoning application, hearings, and approval.
- Plat Approval
- Time for preliminary and final plat review and approval.
- Utility Approvals
- Time for utility plans review and will-serve letters.
- Building Permit
- Time for building permit review and issuance.
- Concurrent Processing
- Percentage of utility and permit phases that can overlap with earlier phases.
How this is calculated
Worked example, using the default values
- Identify Input Parameters4 parametersPre-Application = 2, Environmental Review = 6, Zoning Approval = 4, Plat Approval = 3 = 7 input(s) provided
- Calculate Effective TimelineEffective Timeline17.5 = 17.5
- Calculate TimelineTimeline1.46 = 1.46
- Calculate Sequential TotalSequential Total20 = 20
- Calculate Months SavedMonths Saved2.5 = 2.5
Engine last updated . Checked against 1 independently-derived test — how we verify calculators.
Related Calculators
The questions that sit next to this one — chosen by subject, including calculators filed under a different category.
Land Development
Development Pro Forma Calculator
Create a development pro forma with revenue, costs, profit, and ROI projections.
Land DevelopmentLot Yield Calculator
Calculate the number of buildable lots from raw acreage after deducting roads, open space, and unusable land.
Land DevelopmentAbsorption Rate Calculator
Calculate monthly sales absorption rate, months of supply, and project sellout timeline.
More in Real Estate & Property.