Critical Path Calculator
Calculate critical path duration, ES, EF, LS, LF for project activities.
Inputs
Results
Critical Path Duration
25 days
How to Use This Calculator
- Enter the duration and dependencies for each task in the project.
- The calculator identifies the longest path through the network.
- Review the critical path tasks — any delay here delays the entire project.
- Use float (slack) values for non-critical tasks to optimize resource allocation.
- Update the schedule regularly as tasks complete and durations become known.
How the result changes with Activity 4 (End)
| Activity 4 (End) | Critical Path Duration |
|---|---|
| 100 | 115 days |
| 350 | 365 days |
| 650 | 665 days |
| 900 | 915 days |
What each input means
- Activity 1 (Start)
- Duration of the starting activity (on both paths).
- Activity 2 (Path A)
- Duration of Path A middle activity.
- Activity 3 (Path B)
- Duration of Path B first middle activity.
- Activity 4 (End)
- Duration of the ending activity (on both paths).
- Activity 5 (Path B)
- Duration of Path B second middle activity.
How this is calculated
Worked example, using the default values
- Identify Input Parameters4 parametersActivity 1 (Start) = 5, Activity 2 (Path A) = 8, Activity 3 (Path B) = 6, Activity 4 (End) = 10 = 5 input(s) provided
- Calculate Critical Path DurationCritical Path Duration25 = 25
- Calculate Path A Duration23 = 23
- Calculate Path B Duration25 = 25
Engine last updated . Checked against 2 independently-derived tests — how we verify calculators.
Related Calculators
The questions that sit next to this one — chosen by subject, including calculators filed under a different category.
PERT Estimate Calculator
Calculate weighted duration from optimistic, most likely, and pessimistic estimates.
Project ManagementEarned Value Calculator
Calculate CPI, SPI, EAC, and ETC for project performance tracking.
Construction ManagementCritical Path Method Calculator
Estimate project duration using Critical Path Method (CPM). Calculate critical path length, total float, and schedule compression potential.
Military LogisticsMaintenance Float Calculator
Equipment float sizing from readiness rate and repair time.
Project ManagementAgile Team Capacity Calculator
Calculate sprint capacity accounting for ceremonies and focus factor.
More in Business & Entrepreneurship.