Results
Order Volume (CY)
15.56
Rebar Weight (lbs)
1,164.3
Net Concrete Volume (CY)14.81
Rebar Linear Feet1,660
Rebar Weight (tons)0.58
Formwork Area (SF)60
Concrete Material Cost ($)$2,333.33
Plan Area (SF)800
How to Use This Calculator
- Enter the element length and width in feet and depth or thickness in inches from the structural drawings.
- Select the element type: 0 for a horizontal slab or footing, 1 for a vertical wall.
- Enter the rebar size (#3–#11) and center-to-center spacing in inches.
- Set the waste factor percentage (typically 3–10%) and the concrete unit price per cubic yard.
- Read the concrete order volume in CY with waste included, total rebar linear feet and weight in lbs, formwork area in SF, and concrete material cost.
How the result changes with Length (ft)
| Length (ft) | Order Volume (CY) | Rebar Weight (lbs) |
|---|---|---|
| 1,000 | 388.89 | 28,771.4 |
| 3,500 | 1,361.11 | 100,664.9 |
| 6,500 | 2,527.78 | 186,937.1 |
| 9,000 | 3,500 | 258,830.6 |
What each input means
- Length (ft)
- Element length in feet.
- Width (ft)
- Element width in feet.
- Depth / Thickness (in)
- Slab thickness or wall height in inches.
- Rebar Size (#3–#11)
- Rebar bar size number (e.g., #4 = 0.5 inch diameter).
- Rebar Spacing (in o.c.)
- Center-to-center rebar spacing in inches.
- Waste Factor (%)
- Waste allowance for concrete and rebar (typically 3–10%).
- Element Type (0=Slab, 1=Wall)
- 0 = slab or footing (horizontal), 1 = wall (vertical forms on both sides).
- Concrete Cost ($/CY)
- Ready-mix concrete cost per cubic yard delivered.
What each result means
- Net Concrete Volume (CY)
- Theoretical concrete volume without waste.
- Order Volume (CY)
- Concrete to order, including waste factor.
- Rebar Linear Feet
- Total linear feet of rebar needed.
- Rebar Weight (lbs)
- Total rebar weight including waste.
- Rebar Weight (tons)
- Rebar weight in short tons.
- Formwork Area (SF)
- Square footage of formwork needed.
- Concrete Material Cost ($)
- Ready-mix concrete cost based on order volume.
- Plan Area (SF)
- Total plan area of the element.
How this is calculated
Worked example, using the default values
- Identify Input Parameters4 parametersLength (ft) = 40, Width (ft) = 20, Depth / Thickness (in) = 6, Rebar Size (#3–#11) = 4 = 8 input(s) provided
- Calculate Order VolumeOrder Volume = netVolumeCY * wasteMultiplier15.56 = 15.56
- Calculate Rebar WeightRebar Weight = totalRebarWeight * wasteMultiplier1164.3 = 1164.3
- Calculate Net Concrete VolumeNet Concrete Volume = netVolumeCF / 2714.81 = 14.81
- Calculate Rebar Linear FeetRebar Linear Feet1660 = 1660
Engine last updated . Checked against 2 independently-derived tests — how we verify calculators.
Related Calculators
The questions that sit next to this one — chosen by subject, including calculators filed under a different category.
Construction Estimating
Contingency Calculator
Appropriate contingency percentage from project risk assessment.
Construction EstimatingBond Cost Calculator
Payment and performance bond premium from contract value.
Steel ConstructionSteel Takeoff Calculator
Calculate total steel tonnage from beam and column counts, weights, and lengths for quantity takeoff estimates.
Concrete (Advanced)Rebar Weight Calculator
Calculate rebar weight by bar size, length, and quantity using ASTM A615 standard weights per foot.
Interior ArchitectureMillwork Takeoff Calculator
Custom millwork pricing from design specifications.
More in Construction & Building Trades.